Oklahoma Plumbing Journeyman and Natural Gas License Exam Exam Prep
Free practice questions

Free OK-PLB Practice Questions

10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.

Start the free practice test → ★★★★★4.9/5 from 2,400+ candidates · No signup

The OK-PLB exam has 85 questions and runs 3 hours.

These 10 free OK-PLB questions are organized by exam domain, so you can see how each part of the Oklahoma Plumbing Journeyman and Natural Gas License Exam blueprint is tested. Reveal the answer and explanation under each question.

Domain 1: General Plumbing Knowledge and Regulations

Question 1

On a project governed by Oklahoma's amendments to the 2018 IPC, a new PVC drainage section completes a water test. All piping subject to the minimum-head requirement remains under at least 6 feet of water head for 20 minutes, every joint is tight, and the required overlap with the preceding tested section is included. What should the plumber conclude about this section's pressure test?

Show answer & explanation

Correct answer: B - The completed water test satisfies the required test head and holding time.

Domain 2: Piping, Valves, and Control Valves

Question 2

For a 2-inch PVC drainage joint, a cement label describes a primerless procedure for certain small, nonpressure applications. The work is governed by Oklahoma's amendments to the 2018 IPC. Which joining procedure satisfies the state's requirement?

Show answer & explanation

Correct answer: C - Apply purple primer followed by compatible PVC solvent cement that is not purple.

Domain 3: Fixtures and Equipment

Question 3

A hotel renovation retains ordinary two-handle shower mixing valves that do not compensate for supply changes. A central ASSE 1017 mixing valve limits the hot-water distribution temperature to 120°F. The contractor proposes relying on that central valve for all shower protection. What is required at each individual shower?

Show answer & explanation

Correct answer: D - Install an ASSE 1016 automatic compensating valve with its maximum setting limited to 120°F.

Domain 4: Water Supply

Question 4

After a check valve is added at a building's water service, a plumber investigates recurring pressure increases. With the fixtures closed, pressure is initially 58 psi. It gradually reaches 104 psi as the storage water heater reheats, then returns to 58 psi when a faucet opens. No quick-closing valve operates during the pressure rise. Which condition best explains this pattern?

Show answer & explanation

Correct answer: C - The closed water system lacks effective thermal-expansion control.

Question 5

A lawn-irrigation system supplied from potable water is being fitted with a fertilizer injector and a downstream booster pump. The pump can create backpressure, and downstream valves can keep the line pressurized between irrigation cycles. Which assembly is suitable for this connection under Oklahoma's 2018 IPC requirements?

Show answer & explanation

Correct answer: B - An ASSE 1013 reduced-pressure-principle assembly

Domain 5: Drains and Sewers

Question 6

A new building has a basement finished-floor elevation of 96.0 feet and a ground-floor elevation of 104.0 feet. The next upstream public-sewer manhole cover is at elevation 100.0 feet. Both floors can drain to the sewer by gravity. How should their drainage branches be arranged for backwater protection?

Show answer & explanation

Correct answer: A - Protect the basement branch with a backwater valve; join the ground-floor branch downstream of that valve.

Domain 6: Vents

Question 7

A 2-inch sink trap arm has a developed length of 6 feet before its dry-vent connection. A level survey measures 2-3/4 inches of total fall over that run. The sink drains freely during a water test, and the vent takeoff is otherwise correctly installed. Which revision addresses the trap-arm defect?

Show answer & explanation

Correct answer: A - Reduce the fall before the vent by regrading the arm or moving the vent upstream.

Domain 8: Isometric Analysis

Question 8

The following schematic represents a drainage isometric. J1 and J2 are fixture-branch connections into one vertical soil stack. Segment X is above J2, the highest drainage connection, and continues to the open roof terminal. No other fixture connects to X. Open roof terminal | X | J2 <-- Upper-floor fixture drains | J1 <-- Lower-floor fixture drains | To building drain Which designation belongs on segment X in the piping takeoff?

Show answer & explanation

Correct answer: D - Stack vent

Domain 9: Fuel Gas

Question 9

A new common gas trunk will supply a furnace rated at 120,000 Btu/h input and a water heater rated at 60,000 Btu/h input. The longest developed path from the meter to either outlet is 37 feet. Use the longest-length method and a gas heating value of 1,000 Btu/ft³. The applicable Schedule 40 metallic-pipe table is for natural gas with specific gravity 0.60, inlet pressure below 2 psi, and a permitted pressure drop of 0.5 inch water column. Capacities are in cubic feet per hour: 30-ft row: 1/2 inch = 95; 3/4 inch = 199; 1 inch = 374; 1-1/4 inches = 768. 40-ft row: 1/2 inch = 81; 3/4 inch = 170; 1 inch = 320; 1-1/4 inches = 657. What is the smallest listed size for the common trunk before the appliance branches separate?

Show answer & explanation

Correct answer: C - 1-inch pipe

Domain 10: Safety

Question 10

Two plumbers are working in an unshored sewer trench 4-1/2 feet deep, with a ladder 15 feet away. After a rain shower, the competent person sees new tension cracks and soil sloughing beside their work area. One worker argues that the trench is too shallow to require cave-in protection. What must happen first?

Show answer & explanation

Correct answer: A - Remove the workers from the hazardous area until adequate protective measures are in place.

The rest of the OK-PLB blueprint

The OK-PLB exam also covers these domains. Drill them in the full free practice test:

That's 10 of 1,030

The full bank has 1,020 more OK-PLB questions with explanations.

Continue in the free practice test →

View plans