Question 1
On a project governed by Oklahoma's amendments to the 2018 IPC, a new PVC drainage section completes a water test. All piping subject to the minimum-head requirement remains under at least 6 feet of water head for 20 minutes, every joint is tight, and the required overlap with the preceding tested section is included. What should the plumber conclude about this section's pressure test?
Show answer & explanation
Correct answer: B - The completed water test satisfies the required test head and holding time.